A landscaping and beautification project planned for the corner of 11th Avenue and Old Post Road came closer to fruition on this week.
Sidney city councilors voted to accept bids for the construction at a meeting on Tuesday night. The beleaguered project has faced multiple setbacks since it was proposed last year.
After rising costs and a lack of bids, the construction was broken into three pieces – landscaping, a decorative wall and a sign.
In the 2014-’15 budget, $190,000 was budgeted for the project. The bids approved Tuesday night – including engineering costs – total $277,753....